TechOne CiA migration timeline for digital delivery

Modified on Wed, 22 Oct at 5:49 PM

We recommend a 6–8 week migration timeline to protect your digital delivery:


Week
Milestone
T–6Confirm go-live date with Payreq, bank, and TechOne
T–5Start mapping PRNs or Property IDs to Contact IDs
T–4Begin communications plan development
T–3Complete BPAY View Forms A (activate + deactivate)
T–2Finalise customer letters and approve layout
T–1Freeze subscriptions on old account
Go-liveActivate new account, commence new BPAY View
T+1Perform post-go-live checks, retire old biller


Your Payreq Account Manager will coordinate these steps with you.